The space decides the timeline
Same café, two very different starting points.
Months to open
Typical ranges| Second-generation café | Blank shell | |
|---|---|---|
| Plumbing, floor sinks, grease trap | Often in place | You install them |
| Electrical capacity | Usually sized for food service | Often too small (ours: 50A vs ~200A needed) |
| Drawings | Sometimes minor alterations only | Full architectural, MEP, often structural |
| Health department | Re-inspection of the existing layout | Full plan review of a new layout |
| Risk | Hidden wear on old equipment and lines | Surprise costs uncovered in design |
Who you hire and what they cost
For our 434 square foot shop, professional fees and reviews came to about $30K before construction started. That’s a very small space. The bigger the space, the bigger every one of these numbers gets.
| Professional | What they do | Our cost | Typical range |
|---|---|---|---|
| MEP engineer | Mechanical, electrical, plumbing drawings: panel size, water heater, drains, ventilation | ~$13,000 | $5K–$15K |
| Structural engineer | Anything touching walls, roof or heavy equipment loads | $3,600 | $1.5K–$6K |
| Landlord plan review | Landlord’s team checks drawings against their rules | $3,700 | $0–$5K |
| Architect | Floor plan, finishes, code compliance, the stamped permit set | $10,000 | $5K–$20K, or 8–15% of construction |
| Interior or kitchen designer | Layout, finishes, equipment placement, the look of the room | $0 (I designed it) | Often $5K–$10K more |
| City building permit | Plan review and inspections | Varies | Often a % of construction value |
| Health department | Food establishment plan review and permit | Varies | A few hundred to ~$1K |
The typical permit sequence
Several of these run in parallel, but each one gates the next.
Design Development (DD) set
Rough plans for the landlord and early feedback.
Landlord review
Ours came back “Approved as Noted.” Budget for at least two rounds.
Construction Documents (CD)
The final stamped set, with every review comment addressed.
City permit + health review
Often in parallel. Submit both as early as the drawings allow.
Construction + inspections
Rough-in inspections first, then final.
Health inspection + certificate of occupancy
Then you can open.
Verification beats the cheapest proposal
Saving a few thousand on drawings can cost months. Use this checklist on every architect, engineer and contractor.
Budget vs. actual, as you build
Enter quotes as they come in, then actuals as you pay. It shows what’s left of your contingency.
| Line | Budget ($) | Actual ($) | Over / under |
|---|